Compressed Natural Gas Facility
CTS Builders provided construction management services for a compressed natural gas (CNG) trailer fill facility.
Client: Direct Energy XNG
Location: Manheim, NY
Services: Design Build, Construction Management
The project included interconnect with an Interstate gas mainline with metering and controls. The facility takes transmission pressure gas from the Iroquois Gas Transmission System, LP (1,000 psig) and pressurizes it to 4,000 psig for storage and distribution in road-going trucks and trailers.
Source Pipeline: Iroquois Gas Transmission System, LP
- Inlet pressure: 800 to 1100 psig
- Outlet pressure: 4000 to 5000 psig
- Design flow rate: 1,320 MCFH